Healthpoint Clinic
Delivering over 70,000 sq ft of fit out in a live hospital environment
| Customer | Parsons |
| Project Manager | Aidan Berry |
| Area | 70,000 sq ft |
Adding value every step of the way
In a unique approach to giving back, ISG Middle East launched its first site-based donation drive where over 90 workers working on the site had access to pre-owned outfits.
Engaging with different stakeholders across all areas of the business to ensure it brings the client’s vision to life at every stage of the fit out. The project’s relationship driven approach has seen ISG Middle East working directly with the client on every aspect of the design and build.

The project
Broken down into four phases, ISG Middle East successfully delivered over 70,000 sq ft of fit out in a live hospital environment including:
- Dental Ward
- Medical Screening Clinic
- Aesthetics Clinic
- New Pharmacy
- New Laboratory
- Kitchen Extension
All of the work was carried out in a live environment and this is an area where ISG Middle East’s processes and planned approach to work and minimising disruption really was important to the successful outcome of the project. We are continuing to deliver new projects within the hospital and this is testament to hard work and effort made by all both from ISG but also the consultant and clients teams.

Challenges
The most challenging part of this project was completing the works in a fully operating hospital environment without causing any disruptions to its daily running. To secure the successful outcome of the project, ISG Middle East’s specialist teams implemented processes and a planned approach to working in order to minimise disruption to the client.

ISG Middle East was appointed to undertake four phases of works. The first was to replace three AHUs and associated return air units. The second saw the team install an additional 24 AHUs across the VIP hospital. The third stage included the modifications and upgrades of existing areas to both MEP services and décor. The next stage saw us work on the; dental ward; medical screening clinic; aesthetics clinic; new pharmacy; new laboratory; and a kitchen extension.
Following the successful completion of the first four phases, ISG was tasked with delivering the hospital’s L3 plastics ward – including all medical gas installations, Nurse Call systems and MEP infrastructure resilience with UPS back up for critical equipment. The space was completed in early 2018.