Micro Suites – ICD Brookfield Place

Comprehensive fit out of two floors of service office spaces

Introduction

The project involves the complete fit-out of two floors of services office spaces in the ICD Brookfield Place Building, one of the prime commercial real estate spaces which opened up in Dubai towards the end of 2020. The floors are split into a number of micro office spaces which are being leased out to various tenants as serviced office spaces.

Customer ICD Brookfield Place
Architect Marmol Radziner Associates (USA)
ME Engineer Samadhin Associates
Form Of Contract Lumpsum
Area 36,000 sq ft
Completion Date October 2021
Program Duration 18 weeks
Quantity Surveyor Turner and Townsend

Adding value every step of the way

In a unique approach to giving back, ISG Middle East launched its first site-based donation drive where over 90 workers working on the site had access to pre-owned outfits.

Engaging with different stakeholders across all areas of the business to ensure it brings the client’s vision to life at every stage of the fit out. The project’s relationship driven approach has seen ISG Middle East working directly with the client on every aspect of the design and build.

The project

The scope included the complete fit-out of the space in level 29 and 30, from the shell and core state which includes ceilings, gypsum partitions, glass partitions, staircase connecting the two floors, MEP, AV, IT, security, raised access flooring, carpets, tiles, pantries, server rooms, lobbies and fixed furniture.

The works were executed to a design standard that is in line with the ICD Brookfield Place building standard as well as the design intent of all similar micro suites / flex offices that Brookfield has in various parts of USA.

Challenges

  1. AV/IT/Security scope was initially included in our scope which was later removed partially. Various vendors appointed by Flex IT (Brookfield IT team in the US). This caused hindrances to the progress of work as no solid AV/IT/Security design was finalised.
  2. MRA (Designer) located in the US caused issues and delays in engineering review and approvals.
  3. Landlord power upgrade DEWA approvals were required for fit-out DEWA approvals to proceed

Solution/What We Did

  1. Prepared schematic drawings and sketches which were shared with Flex IT for review and comments thereby bringing clarity to the AV/IT/Security design.
  2. BSBG Architect who is part of the client team and the client project manager were clearly briefed on the engineering submissions which reduced the timelines for receiving responses. Constant follow up with the client providing them weekly updates on approval statuses were exercised so that priorities are set for approvals to align with site execution progress.
  3. Included the impact in the project programme. Installed at site to a draft DEWA design which was approved later. Landlord DEWA final inspection approval obtained as per programme.

ISG delivers a further floor of micro suites in ICD Brookfield Place

ISG Middle East were then further awarded a third level of micro suites – Level 31 – as part of their framework agreement with ICD Brookfield, adding an additional 34,000sqft of space. The scope was the same as previous levels, and was completed on the 27th November 2022 in 24 weeks. Find out more in the video below.

News & Insights

Latest from ISG Middle East

Could appropriate space be the key to resolving our productivity conundrum in the UAE?

ISG Middle East - Madinat Jumeirah Mina Al Salam Royal Suite Living Area 2

Newly refurbished Jumeirah Mina A’Salam Hotel Embodies the Spirit of Arabian Hospitality

The Pivotal Role of Governance in Sustaining Business and Mitigating Risks

ISG Middle East has completed a state-of-the-art workspace project for Roland Berger.